Kherson Thermal Power Plant resumes its work after Russian attacks
Monday, 27 February 2023, 09:40
The Kherson Thermal Power Plant has resumed its work after Russian attacks carried out on 23-24 February 2023.
Source: Press service of the Kherson Oblast State/Military Administration
Details: Houses are already being reconnected to the heating supply system.
Advertisement:
Nevertheless, it will take approximately a day due to technical reasons, specifically because many houses drained the water from their heating systems in order not to let the pipes freeze.
Background: Important equipment and a heating supply transmission line were damaged after attacks on the Kherson Thermal Power Plant.